Which of the following model is a series of short waterfall cycles, each producing an early prototype representing a part of the entire project?
ASpiral
BIterative
CWaterFall
DIncremental
The spiral model works as repeated short waterfall cycles, each giving an early prototype of part of the project.
2.
★ Midterm Spring 2010
The spiral model emphasizes the need to go back and reiterate earlier steps a number of times as the project progresses.
ATrue
BFalse
The spiral model repeatedly goes back over earlier steps as the project progresses.
3.
★ Midterm Spring 2010
The spiral lifecycle model is a combination of the classic RAID model and aspects of risk analysis.
ATrue
BFalse
The spiral model combines the classic waterfall model, not RAID, with risk analysis.
4.
★ Midterm Spring 2011
In which of the following Models it is Difficult to convince some customers that the
evolutionary approach is controllable
ASpiral
BWaterfall
CIncremental
DIterative
A known weakness of the spiral model is convincing customers that the evolutionary approach is controllable.
5.
★ Midterm past paper
Which of the following models is good for large and complex systems?
ASpiral
BIncremental
CWaterFall
DIterative
The spiral model, with its risk analysis, suits large and complex systems.
6.
★ Midterm past paper
In which of the following Models is it difficult to convince some customers that the evolutionary approach is controllable?
ASpiral
BWaterFall
CIncremental
DIterative
A known weakness of the spiral model is convincing customers that the evolutionary approach is controllable.
7.
★ Final term Spring 2010
The spiral life cycle model is a combination of the classic water Fall model and aspects of risk analysis.
ATrue
BFalse
The spiral model combines the waterfall model with risk analysis.
No MCQs match this filter.Is filter mein koi MCQ nahi.
1.
★ Midterm Spring 2011Lecture 213 marks
Discuss the second phase of spiral model along with the steps it involved
Show answerJawab dekhein
The second phase of each spiral loop is evaluating alternatives and identifying and resolving risks. Steps: evaluate the alternatives against the objectives and constraints; identify the areas of risk and uncertainty; resolve them by risk analysis, building prototypes, simulations, benchmarking or user questionnaires; then decide whether and how to proceed to development of the next-level product.
2.
★ Midterm past paperLecture 213 marks
What is Spiral Model?
Show answerJawab dekhein
The spiral model is an iterative approach to system development that combines the classic waterfall model with risk analysis. Development proceeds in loops; each loop determines objectives and alternatives, evaluates alternatives and resolves risks (often by prototyping), develops and verifies the next-level product, and plans the next phase. It emphasizes going back and repeating earlier steps as the project progresses and is suited to large, complex, high-risk information systems.
1.
★ Midterm past paperLecture 215 marks
Situation in which Spiral Model should be used?
Show answerJawab dekhein
The spiral model should be used for large, complex and technically challenging projects that are prone to several kinds of risk, because risk analysis is built into every loop. It suits situations where requirements are unclear or likely to change, where prototypes are needed to clarify them, where the project is long and costly so evaluation at each stage is important, and where new technology is being used. Because it is more complex and needs risk-assessment expertise, it is usually not used for small, ordinary projects. It is called a meta model since it can include the other life-cycle models.
2.
★ Midterm past paperLecture 215 marks
What are the phases of Spiral model?
Show answerJawab dekhein
Each loop of the spiral model passes through four phases: 1) determine objectives, alternatives and constraints of this phase; 2) evaluate alternatives, identify and resolve risks, using risk analysis and prototyping; 3) develop and verify the next-level product (design, code, test); 4) plan the next phase - the customer reviews the results and the next loop is planned. The loops continue until the final system is complete.