Which of the following is not considered Risk Management?
AOn a daily basis, a manager analyses a situation and decides what actions should be taken, if any, given the uncertainties being faced.
BRisk Management addresses actions to resolve a program's problems.
CA systematic approach to setting the best course of action by identifying and acting on risk issues
DAn RBM tool that helps to address potential problems that could interfere with the achievement of results.
Risk management deals with potential future problems under uncertainty, not with resolving problems that already exist.
2.
★ Final term Spring 2008
The objective of the entire risk management process is that no one should hamper the working of the smooth working of IS.
ATrue
BFalse
Risk management aims to ensure nothing hampers the smooth working of the information system.
3.
★ Final term Spring 2010
The identification of risks should start with:
ADescription of the internal and external risks
BA brainstorming session with risk management experts and a program profile
CA good understanding of the program and a brainstorming session with key stakeholders
DDefinitions of likelihood and impact
Risk identification starts from understanding the program and brainstorming with key stakeholders.
4.
★ Final term Spring 2010
A _______________ is the possibility of a problem, whereas a problem is a risk that has already occured.
ARisk
BThreat
CIntrusion
A risk is a potential problem; once it happens it becomes a problem.
5.
★ Final term 2010
A risk is the possibility of a problem, whereas a problem is a risk that has already occurred.
ATrue
BFalse
A risk is a potential problem; once it happens it becomes a problem.
No MCQs match this filter.Is filter mein koi MCQ nahi.
1.
★ Final term Spring 2008Lecture 361 marks
Define Risk Mitigation.
Show answerJawab dekhein
Risk mitigation is the process carried out after risk assessment in which the organization prioritizes, evaluates and implements the risk-reducing controls recommended by the assessment. It chooses options such as risk assumption, avoidance, limitation, planning, research and acknowledgement, or transference so that risk is reduced to an acceptable level at reasonable cost.
2.
★ Final term 2010Lecture 363 marks
Risk mitigation is a process that takes place after the process of risk assessment has been completed. Discuss briefly various risk mitigation options?
Show answerJawab dekhein
- Risk assumption: accept the potential risk and continue operating, or implement controls to lower risk to an acceptable level.
- Risk avoidance: avoid the risk by eliminating its cause, e.g. forgo certain functions or shut down the system when risks are identified.
- Risk limitation: limit the risk by implementing controls that minimize the adverse impact of a threat exercising a vulnerability, e.g. preventive and detective controls.
- Risk planning: manage risk by developing a risk mitigation plan that prioritizes, implements and maintains controls.
- Research and acknowledgement: lower the risk of loss by acknowledging the vulnerability or flaw and researching controls to correct it.
- Risk transference: transfer the risk by using other options to compensate for loss, e.g. purchasing insurance.
3.
★ Final term 2011Lecture 363 marks
what should be kept in mind while identifying the risk?
Show answerJawab dekhein
While identifying risks one should identify the information assets and their value/criticality, the possible threat sources (physical and logical), the vulnerabilities that those threats could exploit, the controls already in place, and the likelihood and impact of each threat. Risk identification should not be confused with risk mitigation, which comes later after risk assessment is complete.
No long questions added yet.Abhi koi long sawal shamil nahi.