Lecture 36: Risk Management

MCQs, short and long questions from lecture 36.Lecture 36 ki MCQs, short aur long sawal.

5 MCQs · 3 short questions · 5 MCQs from past papers5 MCQs · 3 short sawal · 5 MCQs past papers se

Start mock testMock test shuru karein
DoneHal kiye 0/5
– correctsahi
1.
★ Final term Spring 2008

Which of the following is not considered Risk Management?

  1. AOn a daily basis, a manager analyses a situation and decides what actions should be taken, if any, given the uncertainties being faced.
  2. BRisk Management addresses actions to resolve a program's problems.
  3. CA systematic approach to setting the best course of action by identifying and acting on risk issues
  4. DAn RBM tool that helps to address potential problems that could interfere with the achievement of results.

Risk management deals with potential future problems under uncertainty, not with resolving problems that already exist.

2.
★ Final term Spring 2008

The objective of the entire risk management process is that no one should hamper the working of the smooth working of IS.

  1. ATrue
  2. BFalse

Risk management aims to ensure nothing hampers the smooth working of the information system.

3.
★ Final term Spring 2010

The identification of risks should start with:

  1. ADescription of the internal and external risks
  2. BA brainstorming session with risk management experts and a program profile
  3. CA good understanding of the program and a brainstorming session with key stakeholders
  4. DDefinitions of likelihood and impact

Risk identification starts from understanding the program and brainstorming with key stakeholders.

4.
★ Final term Spring 2010

A _______________ is the possibility of a problem, whereas a problem is a risk that has already occured.

  1. ARisk
  2. BThreat
  3. CIntrusion

A risk is a potential problem; once it happens it becomes a problem.

5.
★ Final term 2010

A risk is the possibility of a problem, whereas a problem is a risk that has already occurred.

  1. ATrue
  2. BFalse

A risk is a potential problem; once it happens it becomes a problem.