Which of the following give the excess of available time over the activity time when all jobs start as early as possible?

  1. ATotal float
  2. BFree float
  3. CIndependent float
  4. DEarly finish times

Free float = (E_j - E_i) - t_ij, the spare time when all activities start at their earliest times.