Best possible time estimate that a given activity would take under normal conditions which often exist, is called

  1. AMost Likely time estimate
  2. BPessimistic time estimate
  3. CSmallest time estimate
  4. DActivity time estimate

The most likely estimate is the time the activity would take under normal conditions that occur most often.

2.
★ Final term 2012

In PERT, activity time estimates are distributed according to

  1. ABeta Distribution
  2. BNormal Distribution
  3. CPoisson distribution
  4. DBinomial Distribution

PERT assumes each activity's time follows a beta distribution.

3.
★ Final term Fall 2005

Similarity between CPM and PERT is

  1. ABoth are used to plan the scheduling of individual activities that make up a project
  2. BBoth can be used to determine the earliest/latest stat and finish time for each activity
  3. CAll of the above

Both CPM and PERT schedule project activities and give earliest/latest start and finish times.