Which of the following give the excess of available time over the activity time when all jobs start as early as possible?
ATotal float
BFree float
CIndependent float
DEarly finish times
Free float = (E_j - E_i) - t_ij, the spare time when all activities start at their earliest times.
2.
★ Final term 2012Lecture 9
Best possible time estimate that a given activity would take under normal conditions which often exist, is called
AMost Likely time estimate
BPessimistic time estimate
CSmallest time estimate
DActivity time estimate
The most likely estimate is the time the activity would take under normal conditions that occur most often.
3.
★ Final term 2012Lecture 9
In PERT, activity time estimates are distributed according to
ABeta Distribution
BNormal Distribution
CPoisson distribution
DBinomial Distribution
PERT assumes each activity's time follows a beta distribution.
4.
★ Final term Fall 2005Lecture 9
Similarity between CPM and PERT is
ABoth are used to plan the scheduling of individual activities that make up a project
BBoth can be used to determine the earliest/latest stat and finish time for each activity
CAll of the above
Both CPM and PERT schedule project activities and give earliest/latest start and finish times.
5.
★ Final term Fall 2006Lecture 13
In purchasing model with shortage, the formula of order size is
AQ* = sqrt(2C2D/C3)
BQ* = sqrt(2C2D/C3) sqrt((C3+C4)/C4)
CQ* = sqrt(2C2D/C3) sqrt(R/(R-D))
DQ* = sqrt(2C2D/(C3(1-D/R))) sqrt((C3+C4)/C4)
With shortages allowed, the basic EOQ is multiplied by sqrt((C3+C4)/C4); terms with R belong to manufacturing models.
6.
★ Final term 2012Lecture 17
In a linear Programming Problem (LPP), which of the following must be hold?
AOnly objective function is linear
BBoth objective function and constraints are linear
COnly constraints needs to be linear
DAt least one of objective function or constraint should be linear
An LP model requires a linear objective function and linear constraints.
7.
★ Final term 2012
For any activity backward pass computations provide its
AEarliest start times
BLatest start times
CModerate start times
DCompletion time
The backward pass from the project end gives each activity's latest finish and latest start times.
8.
★ Final term paper (screens, paper 2)
CPM can help you figure out EXCEPT:
Ahow long your complex project will take to complete
Bwhich activities are "critical," meaning that they have to be done on time or else the whole project will take longer
Cwhat is the most costly way to speed up the project
Dyou can try to speed up the project
CPM looks for the least costly way to crash a project, not the most costly.
9.
★ Final term paper (screens, paper 2)
Early finish time of the event '3' in the following project is -------. Network: 1->3 duration 6; 1->2 duration 3; 2->3 duration 5.
A14 days
B2 days
C8 days
D6 days
Event 3 is reached at max(6, 3+5) = 8 days.
10.
★ Final term paper (screens, paper 2)
If shortage cost is infinity, then ..........
Ano shortages are allowed
Bno inventory carrying cost is allowed
COrdering cost is zero
DPurchase cost = Carrying cost
An infinite shortage cost makes any shortage prohibitively costly, so no shortages occur.
11.
★ Final term Fall 2006
In the following network, the critical path is: Network: A(1-2)=5, B(2-3)=7, C(2-4)=9, D(3-5)=11, F(4-5)=9, E(4-6)=3, G(5-7)=2, H(6-7)=4.
AA - B - D - G
BA - C - E - H
CA - C - F - G
DBoth (a) and (c)
A-B-D-G = 25 and A-C-F-G = 25 are both longest, while A-C-E-H = 21.
No MCQs match this filter.Is filter mein koi MCQ nahi.
1.
★ Final term 20122 marks
A firm has normally distributed forecast of usage with MAD = 50 units. It desires a service level, which limits the stock, out to one order cycle per year. Determine Standard Deviation (S. D), if the order quantity is normally a week's supply.
Show answerJawab dekhein
For a normal distribution, standard deviation ≈ 1.25 × MAD. So S.D. = 1.25 × 50 = 62.5 units. (The service level and weekly order quantity are needed only for later parts such as the stockout risk and safety stock: 52 orders/year, 1 stockout/year ⇒ risk 1/52 ≈ 0.019.)
2.
★ Final term paper (screens, paper 2)Lecture 112 marks
What are the key issues of inventory model? Also describe its objective.
Show answerJawab dekhein
Key issues: (1) how much to order (order quantity) and (2) when to order (reorder point/timing). Objective: decide these so that the total inventory cost (purchase, ordering/setup, holding and shortage costs) is minimized while meeting demand.
3.
★ Final term paper (screens, paper 2)Lecture 53 marks
Draw a network diagram for the following dependency relationship. A and B control F; B and C control G.
Show answerJawab dekhein
Events: A = 1->2, B = 1->3, C = 1->4. Dummy D1 = 3->2 (so F also waits for B) and dummy D2 = 3->4 (so G also waits for B). F = 2->5, G = 4->5. Thus F starts after A and B; G starts after B and C; F does not depend on C and G does not depend on A.
1.
★ Final term paper (screens, paper 2)Lecture 185 marks
Wild West produces two types of cow boy hats. Type 1 hat requires twice as much labor time as a type 2. If all the variable labor time is dedicated to type 2 alone, the company can produce a total of 400 type 2 hats a day. The respective market limits for the two types are 150 and 200 hats per day. The profit is Rs. 8 per type 1 hat and Rs. 5 per type 2 hat. Formulate the above linear programming problem. (Note: solution is not required)
Show answerJawab dekhein
Let x1 = type 1 hats/day, x2 = type 2 hats/day. Maximize Z = 8x1 + 5x2 subject to: labor 2x1 + x2 <= 400 (in type-2 hat time units); market limits x1 <= 150, x2 <= 200; x1, x2 >= 0.
2.
★ Final term Fall 20055 marks
Compute Latest start time (LST) and Latest Finish Time LFT for each activity of the following network, if the project is to be completed by the deadline of day 16. Network: A(1-2)=1, B(2-3)=2, C(2-4)=3, dummy (3-4)=0, D(2-5)=4, E(3-5)=5, F(4-5)=6, G(5-6)=6.
How can the linear programming be applied to management problem?
Show answerJawab dekhein
LP helps managers allocate limited resources (money, labour, machines, materials, time) to competing activities to get the best result. Steps: identify decision variables (e.g. units of each product), write a linear objective (maximize profit or minimize cost), express limits as linear constraints, add non-negativity, then solve (graphically or by simplex) and interpret, including sensitivity analysis. Typical management uses: product-mix and production planning, blending/diet problems, transportation and distribution, assignment of staff or machines, advertising media selection, investment/portfolio and capital budgeting, inventory and workforce scheduling.
4.
★ Final term Fall 2006Lecture 1310 marks
Children Hospital Lahore has monthly demand of 6000 units of a tablet named Flagyl. Each tablet cost Rs. 6 and the cost of one purchase is Rs. 950. Keeping that stock for a year in the hospitals cost Rs. 3 per unit. The shortage cost for a year is Rs. 10 per unit, determine the following (i) The Optimum Order Quantity (ii) The time between the orders (iii) The number of orders per year (iv) The Optimum Shortages (v) The time of orders being held
Show answerJawab dekhein
Purchasing model with shortages. Annual demand D = 6000 x 12 = 72,000; ordering cost C2 = 950; holding cost C3 = 3 per unit per year; shortage cost C4 = 10 per unit per year (item cost Rs. 6 does not affect Q*). (i) Q* = sqrt(2 C2 D / C3) x sqrt((C3 + C4)/C4) = sqrt(2 x 950 x 72000 / 3) x sqrt(13/10) = 6752.8 x 1.1402 = 7699 units (about 7700). (ii) Time between orders t = Q*/D = 7699/72000 = 0.1069 year = about 1.28 months (about 39 days). (iii) Orders per year N = D/Q* = 72000/7699 = 9.35 (about 9 to 10). (iv) Optimum shortage S* = Q* C3/(C3 + C4) = 7699 x 3/13 = 1777 units; maximum inventory = Q* - S* = 5922 units. (v) Time during which orders are held as backorders (shortage period) t2 = S*/D = 1777/72000 = 0.0247 year = about 9 days; stock is on hand for t1 = (Q* - S*)/D = 0.0823 year = about 30 days of each cycle.